FG to shut third mainland bridge for three days

FG to shut third mainland bridge for three days

The Federal Controller of Works Lagos, Mr Olukayode Popoola, on Tuesday announced a 72-hour total closure of the Third Mainland Bridge to cast concret

Socialite, Farida Abdulkabir attempts suicide after two months old wedding costing N100m crashes
FG announces traffic diversion plan for third mainland bridge partial closure
Fidelity Bank’s island branches to close at 3pm over Third Mainland Bridge closure

The Federal Controller of Works Lagos, Mr Olukayode Popoola, on Tuesday announced a 72-hour total closure of the Third Mainland Bridge to cast concrete on three expansion joints.

Popoola said that the shutdown will take effect from midnight on Saturday to midnight on Tuesday. He added that construction works had reached the stage for casting concrete on additional three expansion joints.

“There is going to be total closure of Third Mainland Bridge in order to allow for the casting of three number expansion joints on the Island Bound lane. The effective date of the closure will be from 12:00 midnight of 25th of December. So people will be allowed to use the Third Mainland Bridge to celebrate Christmas.

“By the time the Christmas is winding down which is 12:00 midnight, we are going to close it so that we will be able to cast the concrete on Saturday the 26th and 27th we cast again. And we need about 72 hours for this concrete to set. Therefore, the opening will be on the 28th December midnight, that is 72-hour closure.

“This is to prevent vibration of the bridge. If we allow vehicles to be moving on one lane, there is going to be vibrations and the concrete will not set properly,” he said.

The controller said that all the alternative routes were in good condition and traffic regulatory agencies had been deployed to effectively divert and manage traffic to avert gridlock. He appealed to road users to cooperate with traffic regulatory agencies.

Popoola also announced a 48 hours partial closure of the Lagos-Ibadan Expressway from Dec. 28 to Dec. 29 to complete some work on a flyover bridge on the project.
“The contractor, Messers Julius Berger wants to install cross beams at Kilometre 16, that is, around MFM,” he said.

He explained that the Piers were already standing on both sides of the road and the contractor was to lay the cross beam on top across the road.
“That area will be cordoned off, there will be closure within that section from 12:00 pm on 28th of December and it will be opened to traffic by 5:00 am the following day.

“200 meters to get to that particular location we have diversion and another diversion 200 meters away from that place. One lane will be opened to traffic, it is only one lane we are closing to traffic at a time. The first lane that we are going to close is outward Lagos, that is the Ibadan bound carriageway, we will close it on the 28th. And then the second day which is 29th, we are moving to the other lane which in inward Lagos. The same 12:00pm to 5:00am,” Popoola said.

He appealed for patience and understanding of road users saying that the construction was part of the progress that the Federal Government had achieved on the project.
“We regret all the inconvenience and hardship this might have created,” he said.

He said that all the construction zones had been cleared and the highway had been opened to traffic which was responsible to seamless movement on the road.

The Third Mainland Bridge in Lagos, which was going through a series of repairs, had to be partially shut on July 24 for another round of rehabilitation works.

The repair expected to last six months was extended by one month due to the recent #EndSARS protests in Lagos extending the completion date from January 2021 to February.

The construction was initially divided into two phases of three months on each carriageway, starting with the Oworonsoki bound carriageway whose completion dragged to four months.